2026 Road Update

The Town of Canosia has scheduled to add 2-3 inches of gravel to all of the Town gravel roads. There may be some disruptions in traffic flow but no road closures are anticipated. The roads will also be graded after the additional gravel is spread so please be careful if you see trucks hauling, men working, and graders working.

We have also identified four culverts, which are scheduled to be replaced this summer. This too may cause some disruptions, but no road closures.

These improvements and upgrades will be of great benefit to our residents and visitors. Your cooperation is greatly appreciated during the times this work is being done.

I hope you all have an enjoyable and safe summer!

Kevin L. Comnick

Canosia Road Supervisor/Town Board Supervisor

Town of Canosia Driveway Permits

If you are planning to build a driveway on a township road, you will need to download and submit this form: Driveway Permit Application. With the permit application, we will also need two checks: one $35 permit fee and one $250 deposit.  Both should be made out to Canosia Township. The $35 covers the ordering of your new 911 road signage and administrative fees. The $250 check will be returned upon final approval from the township Road Foreman.

Once the permit application and checks have been submitted, construction can begin once the Road Foreman has visited the site and approved the design. Additional rules and instructions can be found on the permit application form.

Please call the Town Clerk 218-260-5600 to arrange a time to drop off the application; Please call the Road Foreman 218-390-3265 with any technical questions or if  the finished driveway is ready for  approval.

Town of Canosia Roads

Road NameRoad NumberLength(miles)Surface
1Alder Road55370.39Gravel
2Birchway Road55380.16Paved
3Carmens Way55290.13Paved
4Christianson Road55280.5Gravel
5Daniels Road55350.56Paved
6Dubla Drive55180.33Paved
7Dunaiski Road55200.24Paved
8Eckstrom Road55310.31Gravel
9Holly Lane55390.15Paved
10Kehtel Road55250.93Paved
11Lakeway Drive55360.12Paved
12Lindahl Road55331.4Paved
13Lockwood Lane55400.5Paved
14Lorendale Road55230.17Gravel
15Nelsondale Road55230.17Gravel
16Pike Lane55720.16Paved
17Pike Lake Place55270.14Paved
18S. Pike Lake Road55320.52Paved
19Shady Lane55261.06Paved, from Kehtel North
Shady Lanefrom Indl to Kehtel
20Spruce Lane55360.42Paved
21Tomak Road55210.45Gravel
22Townline Road55150.9Gravel
23Vaux Road55021.01Paved
24Wilderness Trail55190.49Paved
Total Gravel 2.89
Total Paved8.32
Total Roads11.21

If you have questions or concerns about your township road or upcoming projects, please contact our Road Supervisor Kevin Comnick at 218.590.6743.

All concerns about St. Louis County-owned roads should be directed to their Public Works Dept. at 218.625.3830.